Although every home is unique we take great pride in completing our projects on time and this takes strategic planning, cohesive organization and proper management.  The following time line is a month to month example of how a 12 month construction schedule flows to complete a custom home.   

Pre-Construction

  • Design Concept
  • Final Drawings and Plans
  • Engineering Calculations
  • Plans Submitted for Permitting
Month 1
  • Everest Pre Construction Meeting
  • Pre Construction Selections Due
  • Permits
  • Set Temp Power
  • Excavation
  • Foundation Footings
  • Footing Inspection
  • Foundation Stem wall
  • Wall Inspection
Month 2
  • Install Drain Systems
  • Run Underground Utilities
  • Backfill
  • Basement, Garage and Patio Slabs
  • Framing Starts
Month 3
  • Phase 1 Selections Due
  • Framing Continues
  • Windows Ordered
Month 4
  • Deck Framing
  • Fire Place Framing / CMU
  • Pick up Framing
  • Finish framing
Month 5
  • Plumbing Rough-in
  • Set Temp Water
  • Set Fireplace Units
  • Mechanical Rough-in
  • Electrical Walk Through
  • Start Exterior Masonry
  • Start Exterior Trim
Month 6
  • Window Installation
  • Install Roofing
  • Electrical Rough in
  • Structural Wiring Rough in
  • Mechanical & Electrical Inspections
  • Final Framing Inspection
  • Insulation
  • Insulation Inspection
Month 7
  • Phase 2 Selections Due
  • Sheetrock Tape & Texture
  • Closet Packs
  • Interior Paint
  • Complete Siding
  • Complete Masonry
  • Pavers & Decks
  • Interior Trim Work Starts
Month 8
  • Interior Trim Work Finishes
  • Stain & Lacquer Wood Work
  • Hardwood Installed and Sealed
  • Cabinetry Installed
Month 9
  • Phase 3 Selections Due
  • Tile Work Begins
  • Slab Countertops
Month 10
  • Finish Tile
  • Plumbing Trim out
  • Electrical Trim out
  • Mechanical Trim out
  • Structural wiring Trim out
  • Install Flooring
  • Install Finish Hardware
Month 11
  • Landscaping
  • Exterior Stain
  • Prep Driveway
  • Appliance Installation
  • Company Walk Through
  • Punch List
Month 12
  • Customer Walk Through
  • Fine Tune Punch List
  • Home Cleaning
  • Final Site grading
  • Pave Driveway
  • New Home Orientation and Warranty Manager Meeting, Service Overview
  • Move In

 